Requirement:
In advance of the final phase to complete VAA's new training headquarters
the design team considered it necessary to undertake the raising of part of
the existing roof and formation of numerous feature rooflights together with
other internal major construction adaptations.
Solution:
Following on from the successful completion of the ITC project, LSC were
appointed for the fifth successive time on this site.
The significant part of the works was to raise an 800 m2 area of the existing
roof to accommodate VAA's training rigs hall necessary due to the height
of the aircraft escape platforms planned to be erected as part of the next
phase.
Completion: February 2006
Duration: 23 Weeks
Value: 950K
|